Important links
Hot Links
News Flash
Approved Project
Project -54-Integrated Transit Corridor Development and Street Network / Connectivity Plan for the influence zone of the corridor of Pusta Road from Shastri Park intersection to Sabhapur Border via Khajuri Khas Chowk
| 1. | Name of Project | Integrated Transit Corridor Development and Street Network / Connectivity Plan for the influence zone of the corridor of Pusta Road from Shastri Park intersection to Sabhapur Border via Khajuri Khas Chowk (Length approx. 7 Km) along with detailed design of all intersections and mid-sections based on traffic for the corridor / network. |
| 2. | Name of the Agency | PWD, GNCTD |
| 3. | Copy of Proposal /Presentation | Recommended Option |
| 4. | UTTIPEC Processing |
The project was discussed in UTTIPEC Working Group-II-B meeting under the Chairmanship of Secretary, PWD on 03.05.2017. The observations & recommendations of Working Group-II-B meeting are as follows:
Observations:
Recommendation: Action: PWD, GNCTD 54th Governing body meeting held on 22.06.2017: Observations: Governing body observed that 60m Right of Way (ROW) of Marginal Bund road to be demarcated and if vacant stretch is available along the corridor within the ROW, the same may be developed as green. PWD, GNCTD in consultation with Landscape Department, DDA and other stakeholders to work out the proposal. Decision: Based on the above observations, Governing Body directed PWD to review the proposal of widening of Marginal Bund Road. However, the proposal of vehicular underpass at Khajuri Khas intersection was approved. |
| 5. | Date of Uploading | 23.05.2017 |
| 6. | Additional Details |
Executive Engineer Email id- eepwddelhif31@gmail.com |