1.
|
Name of the Project:
|
Proposal for Comprehensive Development of Corridor (on Ring Road) between Azadpurto Prembari Pul
|
|
2.
|
Name of the Agency
|
PWD, Govt of NCT,Delhi
|
|
3.
|
Consultants:
|
Consulting Engineers Group Ltd.,
207-208, DDA Local Shopping Complex
Vikaspuri, New Delhi-110018
Ph. 28542899, 9313752011
|
|
4.
|
Project Scheduled:
|
- Likely to be started by December, 2010.
- Likely to be completed by June, 2013.
|
|
5.
|
UTTIPEC Processing:
|
- The project of PWD was considered by UTTIPEC Working Group IIB in its meeting dt.16.03.09. and the proposal was recommended for consideration & approval by the UTTIPEC Governing Body with the following decisions / observations :-
-
As far as possible the continuity of interference–free footpaths and cycle tracks at intersections be shown.
-
Traffic management plan/circulation plan for an area of around 1 km. along the both sides of ORR be prepared. Free left turn may be avoided at the intersections, even in case of signalized crossing.
-
Slip roads and service roads wherever feasible, may be provided
-
Width of service road, including footpath, may be at least 7.5 meters.
-
Provisions for segregated lanes and facilities for public transport system, including bus shops, be ensured.
-
Traffic signals be shown at all intersections with provision for separate signal phase for cars, buses, NMT. Signal timings be calculated as per the traffic projections.
-
Location of signage be shown in the plans.
-
The details of effected structures andtrees /bushes be given in the feasibility format.
-
Right of Way line of all roads as per the Master Plan / Zonal Development Planbe shown in the plan. Proposed Right of way(ROW) of Ring Roadto be shownas 63.5mt.(200 ft.) in bold chain line.
-
A traffic management plan and a work zone Management plan during the construction period be prepared.
-
The existing under-pass proposal on the Prembaripul side and the proposed Azad Pur flyover/intersection planbe properly integrated with the proposed corridor plan so as to ensure interference free movement of pedestrians and cyclists.
-
Feasibility report should clearly indicate the location, area, type of affected structures and disputed land/land under stay etc. on the plan/and also in the form of a report which is to be presented before the Governing Body meeting on 20.3.2009.
- UTTIPEC Governing body in its meeting held on 20.3.09 under the chairmanship of Hon'ble L.G, Delhiaccorded itsapproval, based on the recommendation and observation/concern of the working group meetingwith following additional observations:-
- Project must consider clear 11 mtr. elevated road instead of 9 mtr.
-
The need of pedestrians, bus passengers &cyclists be also ensured in micro details, based on input of UTTIPEC core team.
-
To meet the requirement of proper merging & de – merging, length, additional load reservations be made (more than the proposed right of way) at key intersections in the LOP/ZDP/MP.
-
The traffic management / work zone management plan during construction be prepared in consultation with Traffic Police for the influence area of about 1 k.m, on either side of the road.
- Immediately on receipt of the integratedproposal from PWD,GNCTD, with improvements, the same be uploaded on UTTIPEC web site for information of all concerned.
|
|
6.
|
Locatopn Map
|
|
|
7.
|
Copy of the approved plans:
|
|
|
8.
|
For additional details:
|
Kindly contact Project Manager
(Flyover project- circle F-13), PWD, Mukarba Chowk, Delhi
Ph: 27691871, Mob: 9818180952.
|